YOUR BUSINESS AUTHORITY
Springfield, MO
Sapp Design Associates Architects Inc.
Architect: Sapp Design Associates Architects Inc.
Engineers: Olsson Inc., civil and landscape; Toth and Associates Inc., structural; and Interpres Building Solutions LLC, mechanical, electrical and plumbing
General contractor: DeWitt & Associates Inc.
Cost: $39.7 million
Estimated completion: April 15, 2026
Description: In April 2023, voters approved a $220 million bond issue to fund school improvements and projects across the Springfield Public Schools district, including a new facility for Reed Academy. The project includes the demolition of the existing school, completed in November 2023, and reconstruction on the same site for a 128,900-square-foot middle school, project officials say. The building will house a typical SPS middle school program with the addition of an immersive fine arts program to include band, orchestra, choir, art, dance, theater and media broadcasting, clustered around a central multipurpose auditorium and safe room.
April 7 was the official opening day for Mexican-Italian fusion restaurant Show Me Chuy after a soft launch that started March 31; marketing agency AdZen debuted; and the Almighty Sando Shop opened a brick-and-mortar space.
KY3 hires new anchor as Rose prepares for exit
Harry Cooper Supply acquires KC-area company
Fed chair says interest rate changes can wait
Chick-fil-A expansion in the works at MSU
Ozarks Tech presented with 7-figure donation
2 Ameren plants granted Clean Air Act exemptions for 2 years
Defunct solar business sued by Missouri attorney general's office