General contractor: Ross Construction Group LLC
Size: 432,000 square feet
Estimated cost: $15 million, per building permits
Estimated completion: October, Phase I, and early 2021, Phase II
Project description: Ozarks Coca-Cola/Dr Pepper Bottling Co.’s warehouse project is expected to be completed in two phases. The expansion of an existing 125,000 square feet will consolidate staff and operations to a centralized campus from a leased warehouse space near Partnership Industrial Center, company officials have said. The addition also replaces warehousing in the production facility to allow for the expansion of a new bottling line. Buxton Kubik Dodd Design Collective is the project architect and mechanical, electrical and plumbing engineer, while additional engineering work is by Anderson Engineering Inc., civil, and Miller Engineering PC, structural.
Helping people is the foremost purpose in business for Angela Stephens. The idea for Re-Focus the Creative Office was born to help her son, Drake Stephens, who had started struggling in school in fifth grade.
Chick N Max plans Springfield debut
Developer seeks approval of C-Street project, including Missouri Hotel renovation
Executive director hired at The Victim Center
Biblical history attraction planned at former Andy Williams theater
Photo Gallery: New Fire in the Hole debuts at Silver Dollar City