From the Ground Up: Strafford Fire Station No. 3

300 W. Bumgarner Blvd., Strafford

Posted online

Owner: Strafford Fire Protection District
General contractor: Rich Kramer Construction Inc.
Architect: FGM Architects (Oak Brook, Illinois)
Engineers: Great River Engineering Inc., civil and structural; and SSC Engineering Inc. (Chesterfield), mechanical, electrical and plumbing
Size: 7,029 square feet
Cost: $3.5 million
Funding source: Proposition Fire general obligation bond
Estimated completion: October
Project description: A new fire station is in the works on the south side of Strafford, near the Southwest Missouri Rail and Industrial Park, to serve the growing community. The project is funded through an $8 million general obligation bond, called Proposition Fire, that voters approved in April 2022 to build Station No. 3, renovate Station No. 2 and buy new fire apparatus, among other needs. The firehouse will feature two truck bays, five bunk rooms, a kitchen, workout room and training and community room, according to officials from general contractor Rich Kramer Construction. Strafford’s population is on the rise, according to U.S. Census Bureau figures which show it increasing from 2,020 in 2004 to 2,720 this year – almost 35% in the span of two decades.

Comments

No comments on this story |
Please log in to add your comment
Editors' Pick
Business of the Arts: Full Moon

New Moon Studio Space operating at capacity in year two.

Most Read
Update cookies preferences